AES frequently asked questions
Answers to common questions about Western Australia's Alternative Electricity Services (AES) framework, for Single Property Network (SPN) and on-site power supply (OPS) providers. Each answer lists the law or official document it's based on.
About these answers.
The Electricity Industry (Alternative Electricity Services) Regulations 2026 and the Alternative Electricity Services Code of Practice 2026 (which covers OPS providers) are law. The obligations for SPN providers are proposed in a draft Code of Practice and may change before the Code is made. Answers last checked 25/11/2026.
Timeline and status
Registration for on-site power supply (OPS) providers, such as solar power purchase agreement providers, is required from 1 February 2027. Registration for Single Property Network (SPN) providers is required from 1 July 2027. Providers register with the Economic Regulation Authority (ERA). The ERA expects its online portal to be open and accepting applications from mid-January 2027, and will announce the date closer to the time.
If you're already providing an OPS service on 1 February 2027, you're taken to be registered from that date. If you apply before 1 March 2027, that continues until the ERA decides your application. If you don't apply in time, it ends at the beginning of 1 March 2027. The ERA says existing OPS providers must apply by 28 February 2027.
The same applies to SPN providers already supplying on 1 July 2027, with an application deadline of before 31 July 2027.
The Electricity Industry (Solar Power Purchase Agreements) Exemption Order 2016 is repealed from 1 March 2027.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulations 9 and 19. ERA, Information for AES providers. Electricity Industry (Solar Power Purchase Agreements) Exemption Amendment and Repeal Order 2026, clause 5.
Partly.
- The Electricity Industry (Alternative Electricity Services) Regulations 2026 were published on 5 August 2026. They set out which services must be registered, who can register, the arrangements for existing providers, and the fees.
- The Alternative Electricity Services Code of Practice 2026 was published on 12 August 2026. It sets out the obligations for OPS providers. It is law, and its obligations take effect on 1 February 2027.
- The obligations for SPN providers are still a draft. Energy Policy WA released a draft Alternative Electricity Services Code of Practice 2027 for comment. It would replace the 2026 Code with one Code covering both OPS and SPN services, with SPN obligations starting on 1 July 2027. Consultation closed on 25 September 2026, with 38 submissions. As at 25 November 2026, no final SPN Code has been made.
So the SPN obligations described on this page are those proposed in the draft Code, and they may change before the Code is made.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026 (SL 2026/163). Alternative Electricity Services Code of Practice 2026 (SL 2026/167). Energy Policy WA, AES Code of Practice for Single Property Network Services consultation.
Registration
Supplying electricity to residents through a building's own electricity network, known in the framework as a Single Property Network (SPN), is an alternative electricity service. Providing one without registration is an offence. So if your strata company buys electricity at the building's parent meter and supplies it to residents, it will need to be registered from 1 July 2027, unless:
- another eligible company holds the registration for the network. Only one registration can be granted for each SPN, and anyone else supplying electricity within that SPN is then exempt from registering;
- the supply is an "excluded supply". One example is a strata company supplying residents of a strata scheme with no more than 10 lots, where the land is used only for residential purposes; or
- the electricity isn't charged for separately and is incidental to providing other goods or services.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulations 10, 11 and 12. Electricity Industry Act 2004, section 59D.
Two kinds of party can apply to register an SPN:
- the account holder: whoever buys, or intends to buy, electricity at the network's parent meter. This is often the strata company; or
- another party that supplies, or intends to supply, electricity within the network.
A billing contractor can register only if it supplies, or intends to supply, the electricity itself. Only one registration can be granted for each SPN.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulation 11.
Yes, if it supplies, or intends to supply, electricity within your building's network. Once another party holds the registration for the network, anyone else supplying electricity within it, including your strata company, is exempt from registering. The registration holder must take reasonable steps to make sure anyone else who supplies electricity within the network also complies with the AES Code of Practice.
Bright Connect will register under the AES framework. Under our Full Risk Transfer model, Bright Connect becomes the registration holder for your network, and all regulatory risk transfers to Bright Connect. Under our Operational Support model, your strata company holds the ERA registration and Bright Connect delivers all operational compliance.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulations 11, 12 and 15(2).
Applying is free: the application fee is nil. There is an annual fee, worked out as the ERA's yearly costs divided by the number of registrations. The State Government estimates it at around $300 per registration. The ERA expects to send the first invoice in August 2028, for the period 1 July 2027 to 30 June 2028.
Energy and Water Ombudsman WA membership has its own costs. Most AES providers will pay a small joining levy, plus annual levies and dispute costs. The Ombudsman's usual $5,000 joining fee doesn't apply to AES providers.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulations 22 and 23. ERA, Information for AES providers. Energy and Water Ombudsman WA, Alternative electricity services.
Provider obligations
The SPN obligations in this section are proposed in the draft SPN Code and may change before the Code is made.
The draft SPN Code proposes that SPN providers:
- issue a bill at least once every 2 months, unless the provider and the customer agree a billing period;
- show on each bill the provider's name, ABN and contact details, the customer's account number, the meter identification number, the billing period, the amount due and the due date, any amount owed or in credit, other fees, the GST for each amount, how to pay, and a telephone number and email address for billing and payment enquiries;
- not charge a fee for a paper bill; and
- keep billing data for at least 2 years.
The draft also proposes a "standard tariff" for small-use customers. For a residential customer, the daily supply charge and the charge per unit used couldn't be more than those in Synergy's A1 residential tariff, unless the customer opts into a special tariff offered by the provider.
OPS providers already have similar billing rules, which take effect on 1 February 2027.
Sources: Draft Alternative Electricity Services Code of Practice 2027, clauses 22 to 25 and 32 to 35. Alternative Electricity Services Code of Practice 2026, clauses 21 to 24.
Yes. The Alternative Electricity Services Code of Practice 2026 requires OPS providers, and the draft SPN Code proposes for SPN providers, a hardship policy that the provider develops, maintains and puts into practice. It is for residential customers who have trouble paying because of financial hardship. Among other things, the policy must encourage customers to get in touch, explain how hardship customers are identified, offer extra time to pay through a payment plan, say the provider will consider reducing or waiving fees, charges or debt, and explain how to find financial counselling. A payment plan can't include set-up or administration fees, or interest.
Providers also need a separate family violence policy, covering confidentiality, a safe way to communicate, flexible payment options, and reviewing a customer's circumstances before acting on an unpaid amount. A provider must not require written evidence of family violence from a residential customer.
A provider with a website must publish both policies on it.
Sources: Alternative Electricity Services Code of Practice 2026, clauses 4, 7 and 29 to 32. Draft Alternative Electricity Services Code of Practice 2027, clauses 40 to 43.
Yes, if you supply electricity to small-use customers. Providers that supply electricity to small-use customers must become members of the Energy and Water Ombudsman WA Scheme, which gives customers access to an independent dispute resolution process. One membership covers all of a provider's properties. While an existing provider is taken to be registered under the arrangements for existing providers, it's also taken to be a member.
You'll also need your own complaints and dispute resolution procedure, consistent with the Australian Standard AS 10002:2022, Guidelines for complaint management in organizations. You must tell a customer the outcome of a written complaint, with reasons, within 20 business days, and tell small-use customers they can take it to the Ombudsman. You can't charge a fee for dealing with a complaint. These rules are in the OPS Code of Practice, and proposed in the draft SPN Code.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulations 9(3) and 19(3). Alternative Electricity Services Code of Practice 2026, clauses 36 and 37. Draft Alternative Electricity Services Code of Practice 2027, clauses 50 and 51. Energy and Water Ombudsman WA, Alternative electricity services.
The draft SPN Code proposes that SPN providers keep a life support register: the address of each home where someone who needs life support equipment lives, and contact details for the customers there. Under the draft, a provider would need to:
- update the register within 48 hours of receiving a medical practitioner's confirmation, and give a copy to the network's electricity retailer;
- within 10 days, give the customer written information about possible interruptions and how to prepare for one;
- check at least once a year that the register is accurate;
- make sure registered customers know about planned interruptions, as well as giving the usual written notice; and
- not disconnect a registered address for unpaid bills.
The Alternative Electricity Services Code of Practice 2026 has no life support register requirement for OPS providers.
Sources: Draft Alternative Electricity Services Code of Practice 2027, clauses 45(6)(c), 49(2)(b) and 52 to 54. Alternative Electricity Services Code of Practice 2026.
OPS services (solar and battery arrangements)
An on-site power supply (OPS) service is an arrangement that lets a person use electricity from a system that produces or stores electricity, such as solar panels or a battery, where:
- the person doesn't own the system;
- the system is installed on the land they occupy, or on the same property as an SPN that supplies them;
- the arrangement sets the terms for using the electricity, for example a price per kWh, or a membership or subscription fee; and
- the person also gets electricity from a retailer or within an SPN.
Solar power purchase agreements are one example.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulation 4.
Anyone providing an OPS service needs to be registered with the ERA from 1 February 2027. That includes solar power purchase agreements, battery arrangements and similar services where you own the system and the customer pays to use the electricity.
If you're already providing an OPS service on 1 February 2027, you're taken to be registered until the ERA decides your application, but only if you apply before 1 March 2027. The ERA says existing OPS providers must apply by 28 February 2027.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulations 4 and 9. ERA, Information for AES providers.
Yes. An arrangement is only an OPS service if the customer is also supplied with electricity on the land by a retailer or within an SPN. The provider's disclosure statement and agreement must say whether the system can run independently of that supply.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulation 4(2)(d). Alternative Electricity Services Code of Practice 2026, clauses 10(3)(i) and 11(1)(i).
At least 10 business days. An OPS agreement must include a cooling-off period of at least 10 business days, during which the customer can end the agreement by giving the provider written notice.
Sources: Alternative Electricity Services Code of Practice 2026, clause 11(2)(a).
The OPS Code of Practice doesn't set OPS prices. It controls how they're disclosed and changed:
- before an agreement is signed, the disclosure statement must show the estimated costs for the first 12 months, the price per unit and all fees and charges;
- the provider must give at least 5 business days' notice of a price change, and the change can't apply before the next billing period starts unless the customer agrees another date; and
- late payment fees must not be unreasonable.
Sources: Alternative Electricity Services Code of Practice 2026, clauses 10, 13 and 14.
Disconnection here means stopping electricity from the OPS system, not the customer's main supply.
If a customer hasn't paid an amount by its due date and hasn't entered a payment plan, the provider must wait at least 15 business days after the due date, then send a copy of the bill with a written notice. The notice must include the number for billing enquiries, the hardship and family violence policies (for residential customers), the complaints procedure and Ombudsman information, and a statement that the system may be disconnected at least 10 business days later. If the customer still hasn't paid or entered a payment plan by then, the provider may arrange disconnection.
This process can't be used for amounts under $100, for amounts that don't relate to the supply of electricity, or while a complaint or dispute the customer has raised with the provider is unresolved. Once the customer pays or enters a payment plan, the provider must arrange reconnection within 2 business days, and may charge a reasonable reconnection fee.
Sources: Alternative Electricity Services Code of Practice 2026, clauses 33 to 35.
Yes. From 1 February 2027, an OPS provider must develop, maintain and put into practice a hardship policy for residential customers who have trouble paying because of financial hardship, and must consider a reasonable request for a payment plan from a non-residential customer in the same position. It also needs a family violence policy, and must not require written evidence of family violence from a residential customer. See "Do we need a hardship policy?" above for what each policy must include.
Sources: Alternative Electricity Services Code of Practice 2026, clauses 29 to 32.
The Electricity Industry (Solar Power Purchase Agreements) Exemption Order 2016 is repealed from 1 March 2027, by the Electricity Industry (Solar Power Purchase Agreements) Exemption Amendment and Repeal Order 2026, published on 28 October 2026.
Registration for OPS providers, such as solar power purchase agreement providers, is required from 1 February 2027. A provider already supplying on 1 February 2027 is taken to be registered until the ERA decides its application, if it applies before 1 March 2027.
Sources: Electricity Industry (Solar Power Purchase Agreements) Exemption Amendment and Repeal Order 2026 (SL 2026/221), clause 5. Electricity Industry (Alternative Electricity Services) Regulations 2026, regulation 9.
No. The Alternative Electricity Services Code of Practice 2026 doesn't include a life support register requirement for OPS providers. It does require the disclosure statement and the OPS agreement to say whether the system can operate independently of the customer's other electricity supply.
Sources: Alternative Electricity Services Code of Practice 2026, clauses 10(3)(i) and 11(1)(i).
EV charging
EV charging supplied through your building's own network is a supply of electricity within the SPN, so it's covered by the SPN rules unless an exclusion applies. One exclusion is an EV charging station available to the general public on a user-pays basis.
The draft SPN Code proposes rules for charging separately for EV supply. A provider could charge it as a standard or special tariff, any fixed daily charge for it couldn't be more than the additional dwelling amount in Synergy's A1 tariff, and the provider would need to give written notice before limiting EV supply.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulation 10(2) and 10(3)(i). Draft Alternative Electricity Services Code of Practice 2027, clause 26.
Exclusions
Supplying electricity within an SPN isn't an alternative electricity service if it isn't charged for separately and is incidental to providing other goods or services. Whether electricity included in rent or levies meets that test depends on the arrangement. If electricity is charged for separately, this exception doesn't apply.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulation 10(2)(b).
No. Supply to temporary accommodation is an excluded supply. Temporary accommodation means accommodation occupied by the same person for a total of no more than 3 months, continuously or from time to time, in any 12-month period.
Sources: Electricity Industry (Alternative Electricity Services) Regulations 2026, regulation 10(3)(h).
Penalties
Under the Electricity Industry Act 2004:
- providing an alternative electricity service without registration is an offence, with a fine of up to $100,000, plus up to $5,000 for each day the offence continues (section 59D);
- failing to comply with the terms and conditions of a registration is an offence, with a fine of up to $100,000, plus up to $5,000 for each day the offence continues (section 59E); and
- the ERA itself can order a monetary penalty of up to $100,000 (section 59ZI(2)(c)).
Sources: Electricity Industry Act 2004, sections 59D, 59E and 59ZI(2)(c).
Still have questions?
Talk to the Bright Connect team on 1300 908 760 or at connect@brightconnect.com.au.
General information only. Not legal advice.
Checked against official sources on 25/11/2026. Sources: AES Regulations 2026; AES Code of Practice 2026 (OPS); Draft SPN Code consultation; Solar PPA exemption repeal order; ERA information for AES providers; Energy and Water Ombudsman WA.
Ready to switch on smarter energy?
Talk to our team about your building today.